Actual rooftop at Villa Lantana
Blue Iconic Group LLC · Proposal

Roof Waterproofing Proposal

Villa Lantana, Dubai

Two carefully prepared waterproofing solutions for your villa roof, with a clear overview of the proposed works, investment and important technical considerations.

Roof area
200 sqm (provisional)
Proposal date
26 October 2026
Location
Villa Lantana, Dubai
Solutions
PU · EPDM
01 · The Project

Understanding Your Roof Waterproofing Project

Both options cover the same complete scope around the roof — only the waterproofing system itself differs. Here is what the works include, in plain terms.

Roof waterproofing

A complete waterproofing system across the roof — PU or EPDM, depending on the option you choose.

Surface preparation & repairs

Cleaning the exposed substrate, repairing cracks and making good defects before any new layer goes down.

Gravel & geotextile

Careful lifting, temporary storage and reinstatement of the existing gravel, with damaged fabric replaced.

Drains

Inspecting and clearing accessible drains, with removable gravel guards and access covers at existing drain points.

Parapets, junctions & penetrations

Upstands nominally 300 mm above the finished roof where feasible, with pipes and ducts sealed using compatible details.

Water tank & pump zone

Treating the accessible equipment zone; any lifting or shifting only with safe access and specialist approval.

Wall coping & gaps

Localized repair of open gaps and defective concrete or coping junctions.

AC pipe insulation

Provisional allowance for UV-protected insulation and cladding on damaged refrigerant lines; condensate pipes inspected.

Quality checks & handover

Documented inspection, controlled water testing where permissible, thermal screening, photos and warranty documents.

The roof area of 200 sqm is provisional. Final system compatibility, quantities and any concealed conditions remain subject to site survey.

02 · On Site

A Closer Look at the Roof

A short walk across the roof shows the environment the works will take place in — useful context for the scope described in this proposal.

Actual Project Footage

What the footage shows

  • A flat roof finished with loose gravel ballast and paved walkways
  • A water tank under a timber shade structure, with a pump set and control panel
  • Several AC condensing units with insulated pipe runs across the roof
  • Parapet walls, upstands and enclosed service housings

This is a visual overview only, not a technical diagnosis. Conditions will be confirmed during the site survey.

04 · Side by Side

Comparing PU and EPDM

Everything that is the same is marked as such, so the real differences are easy to see.

Option 1
Reinforced Liquid PU
Option 2
1.5 mm EPDM Single-Ply
Waterproofing system
Manufacturer-approved reinforced liquid PU
1.5 mm EPDM single-ply membrane
Quotation
BIG-RF-PU-200-1026
BIG-RF-EPDM-200-1026
Roof areaSame
200 sqm (provisional)
200 sqm (provisional)
Main waterproofing item
AED 29,000.00
AED 37,000.00
Supporting works (items 2–11)Same
AED 48,200.00
AED 48,200.00
Subtotal
AED 77,200.00
AED 85,200.00
VAT (5%)
AED 3,860.00
AED 4,260.00
Workmanship warrantySame
7 years
7 years
Estimated durationSame
20–30 working days
20–30 working days
Payment termsSame
40% · 40% · 20%
40% · 40% · 20%
Quotation validitySame
15 days
15 days
Grand total incl. VAT
AED 81,060.00
AED 89,460.00

Difference between the two options: AED 8,400.00 including VAT, arising entirely from the main waterproofing item.

06 · Good to Know

Clarifications, Exclusions & Warranty

These conditions apply equally to both options. We've kept the wording from the quotations so nothing is lost in translation.

Suggested payment terms
40%
Advance
40%
After membrane installation
20%
After handover
Programme
Estimated 20–30 working days
Warranty
7 years workmanship
Validity
15 days
Existing insulation & gravel

Existing roof insulation foam and fabric are retained only if dry, sound and compatible. Replacement of damaged or wet materials is extra. Existing gravel is reinstated where reusable.

Drains

Drain clearing and accessible removable gravel guards included; concealed pipe repairs, new drains and extensive regrading excluded.

Upstands

Waterproofing upstands target approximately 300 mm above finished roof level wherever practical; termination details subject to wall configuration.

Water tank & pump area

Water tank and pump area is included for accessible surfaces. Specialist tank emptying, disconnection, lifting and electrical reconnection are excluded pending site inspection.

AC refrigerant pipes

AC refrigerant pipe insulation and UV-protected fittings: AED 7,800 provisional allowance included; exact lengths and required HVAC works subject to survey.

Optional thermal insulation

Optional higher-performance PIR/XPS thermal insulation: AED 95/sqm plus VAT, not included; system design, loading and condensation review required.

Testing

Controlled water testing where safe and thermal imaging screening are included; no flood testing where loading or equipment safety prevents it.

Warranty

Seven-year Blue Iconic Group workmanship warranty subject to approved full-system installation, maintenance and written handover. Manufacturer-backed warranty is not promised unless confirmed in writing.

Programme & payment

Estimated 20–30 working days subject to approvals, roof condition and weather. Suggested payment terms: 40% advance, 40% after membrane installation, 20% after handover.

Approvals & validity

Villa Lantana community NOC/access documentation will be prepared as applicable; third-party approval charges excluded. Validity 15 days. All quantities and concealed defects subject to site survey.

07 · Moving Forward

Your Next Steps

Whenever you're ready, we'll guide you through each stage. This quotation is valid for 15 days from 26 October 2026.

  1. 01

    Choose your option

    Let us know whether you prefer the PU or EPDM solution.

  2. 02

    Site survey

    We confirm compatibility, quantities and any concealed conditions on the roof.

  3. 03

    Approvals

    Villa Lantana community NOC and access documentation prepared as applicable.

  4. 04

    Works & handover

    Installation, quality checks, photographs and written warranty handover.

Client Approval
Company Stamp